QCI-NABET accreditation of EIA consultant organisations Environmental Impact Assessment & Strategic Environmental Assessment: practice questions

QCI-NABET accreditation of EIA consultant organisations (EIA Coordinator and Functional Area Expert approval) · India · National Accreditation Board for Education and Training, Quality Council of India

Original practice questions written to the published syllabus · not past papers
7worked here, free
39written to this exam in this subject
14syllabus units

What this subject covers

The full EIA process as a practitioner runs it: screening, scoping, baseline studies, impact prediction, significance, mitigation hierarchy, environmental management plans, public consultation, review and follow-up, plus SEA and social impact assessment. The Agribusiness subject natural-resource-environmental-economics and the Agricultural Engineering waste subject each carry a one-unit introduction to EIA; this is the full subject.

In the exams: GATE ES Section 9; ICAR AICE subject 71 Unit 3; UGC NET Unit 8; China EIA engineer licence; EIANZ Impact Assessment specialist; NABET EIA coordinator roles

Where the 39 questions fall

How our questions for QCI-NABET accreditation of EIA consultant organisations spread across the units of Environmental Impact Assessment & Strategic Environmental Assessment. Difficulty: 12 easy, 23 medium, 4 hard.

Baseline data collection5
Impact prediction and evaluation of significance5
Screening and categorisation of projects4
Scoping and terms of reference4
Environmental management plans and monitoring4
Legal frameworks: NEPA, EU EIA Directive, India EIA Notification and others3
Mitigation hierarchy: avoid, minimise, restore, offset3
Public consultation and hearings3
EIA review, decision-making and environmental clearance3
History, purpose and principles of EIA1
Impact identification: checklists, matrices, networks, overlays1
Cumulative impact assessment1
Social impact assessment1
Lender standards: IFC Performance Standards and Equator Principles1

7 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

1 · Legal frameworks: NEPA, EU EIA Directive, India EIA Notification and others · easy

Under India's EIA Notification 2006, which body appraises Category A projects?

  1. The Expert Appraisal Committee for the central environment ministry
  2. The State Expert Appraisal Committee
  3. The district collector's office
  4. The State Pollution Control Board alone
Answer and working

A. The Expert Appraisal Committee for the central environment ministry

Category A projects are appraised at central level by Expert Appraisal Committees advising the MoEFCC; Category B projects go to SEIAA advised by SEAC. The SPCB conducts public hearings but does not appraise.

Further reading: EIA Notification 2006 (India), as amended

2 · Legal frameworks: NEPA, EU EIA Directive, India EIA Notification and others · easy

Which four stages make up the environmental clearance process under India's EIA Notification 2006?

  1. Planning, design, construction and commissioning of the project
  2. Screening, scoping, public consultation and appraisal
  3. Inspection, sampling, prosecution and closure of the industry
  4. Application, payment, inspection and automatic approval after 30 days
Answer and working

B. Screening, scoping, public consultation and appraisal

The Notification sets screening (Category B only), scoping (ToR), public consultation and appraisal. The other sequences describe project phases, enforcement or an invented deemed-approval process.

Further reading: EIA Notification 2006 (India), as amended

3 · Scoping and terms of reference · medium

For a large canal irrigation project, which issue would scoping most clearly identify as key?

  1. Electromagnetic radiation from mobile phone towers in nearby towns
  2. Waterlogging and salinity in the command area and reduced flows downstream
  3. Radioactive waste storage at the project headworks
  4. Light pollution affecting astronomical observatories
Answer and working

B. Waterlogging and salinity in the command area and reduced flows downstream

Irrigation schemes typically raise water tables and salinity without drainage, and diversions reduce downstream flows for ecosystems and users; resettlement and vector-borne disease are other common issues. The other options are not typical of irrigation.

Further reading: FAO irrigation and drainage EIA guidance

4 · Impact identification: checklists, matrices, networks, overlays · medium

For comparing alternative routes of a pipeline through sensitive landscapes, which method is most suitable?

  1. Weighted GIS overlay analysis
  2. A simple checklist of impact types
  3. A questionnaire checklist sent to the proponent
  4. An ad hoc expert panel without maps
Answer and working

A. Weighted GIS overlay analysis

Overlay analysis in GIS maps habitats, slopes, settlements and heritage along each corridor and scores suitability, which suits spatial comparison of routes. Checklists and ad hoc panels lack spatial analysis.

Further reading: Glasson and Therivel, Introduction to EIA

5 · Impact prediction and evaluation of significance · medium

Settlement and roadside businesses springing up along a new rural road are an example of what kind of impact?

  1. Direct impact
  2. Residual impact
  3. Induced impact
  4. Transboundary impact
Answer and working

C. Induced impact

Induced impacts arise from activities the project stimulates. Direct impacts are caused by the project itself (land take for the road); residual impacts remain after mitigation; transboundary impacts cross borders.

Further reading: Glasson and Therivel, Introduction to EIA

6 · Mitigation hierarchy: avoid, minimise, restore, offset · medium

Why do mitigation measures often fail to be implemented?

  1. Because EIA law forbids proponents from paying for any mitigation measure
  2. Because mitigation can be implemented only after the project is decommissioned and the site cleared
  3. Because regulators require all mitigation to be done by the public
  4. They are described in the EIA but not carried into the EMP, clearance conditions and contracts
Answer and working

D. They are described in the EIA but not carried into the EMP, clearance conditions and contracts

Measures need an owner, budget, schedule and indicator, and must appear in the EMP, conditions and contractor documents; otherwise they are forgotten. The other statements are false.

Further reading: Glasson and Therivel, Introduction to EIA

7 · Cumulative impact assessment · hard

Baseline PM10 at a village is 72 µg/m³ against a standard of 100 µg/m³. Three proposed plants are each predicted to add 10 µg/m³ there. What is the cumulative concentration?

  1. 82 µg/m³, which meets the standard
  2. 30 µg/m³, which meets the standard
  3. 172 µg/m³, which exceeds the standard
  4. 102 µg/m³, which exceeds the standard
Answer and working

D. 102 µg/m³, which exceeds the standard

Cumulative = 72 + 3 × 10 = 102 µg/m³ > 100: each plant alone (82) appears acceptable but together they breach the standard. 30 ignores the baseline; 172 adds the standard.

Ten here, 39 in the app. The Laisha app has every practice question we have written to QCI-NABET accreditation of EIA consultant organisations in this subject, marked as you go, with timed papers, a jump-to-unanswered list and a certificate when you pass at 70 per cent.

Free for ten days, then one subscription of US$10 a month. We would rather say so here than have you find it later.

Practise the full set in Laisha →

Read the subject

Environmental Impact Assessment & Strategic Environmental AssessmentThe full study manual, free QCI-NABET accreditation of EIA consultant organisationsFormat, sections and how it has changed

Environmental Impact Assessment & Strategic Environmental Assessment for other exams

UGC NET · IndiaCertified Environmental Practitioner and specialist certifications · Australia / New ZealandGATE · India

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.