GATE Environmental Impact Assessment & Strategic Environmental Assessment: practice questions

GATE — Environmental Science and Engineering (ES) · India · IITs and IISc on rotation (2026: IIT Guwahati)

Original practice questions written to the published syllabus · not past papers
10worked here, free
39written to this exam in this subject
12syllabus units

What this subject covers

The full EIA process as a practitioner runs it: screening, scoping, baseline studies, impact prediction, significance, mitigation hierarchy, environmental management plans, public consultation, review and follow-up, plus SEA and social impact assessment. The Agribusiness subject natural-resource-environmental-economics and the Agricultural Engineering waste subject each carry a one-unit introduction to EIA; this is the full subject.

In the exams: GATE ES Section 9; ICAR AICE subject 71 Unit 3; UGC NET Unit 8; China EIA engineer licence; EIANZ Impact Assessment specialist; NABET EIA coordinator roles

What GATE asks from it

GATE — Environmental Science and Engineering (ES), Section 9

EIA process steps, screening and scoping, methods (checklists, Leopold matrix, networks, overlays, Battelle), impact prediction numericals (noise attenuation and decibel addition, mixing, dispersion), significance, EMP and Indian EIA Notification 2006 categories and stages.

Where the 39 questions fall

How our questions for GATE spread across the units of Environmental Impact Assessment & Strategic Environmental Assessment. Difficulty: 16 easy, 18 medium, 5 hard.

Impact identification: checklists, matrices, networks, overlays9
Impact prediction and evaluation of significance6
Screening and categorisation of projects4
History, purpose and principles of EIA3
Legal frameworks: NEPA, EU EIA Directive, India EIA Notification and others3
Scoping and terms of reference3
Baseline data collection3
Environmental management plans and monitoring2
Cumulative impact assessment2
Strategic environmental assessment2
Mitigation hierarchy: avoid, minimise, restore, offset1
Public consultation and hearings1

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

1 · History, purpose and principles of EIA · easy

Which law, signed on 1 January 1970, was the first to require environmental impact assessment?

  1. The US National Environmental Policy Act
  2. The UK Town and Country Planning Act 1947
  3. India's Environment (Protection) Act of 1986
  4. The EU Environmental Impact Assessment Directive
Answer and working

A. The US National Environmental Policy Act

NEPA (1969, signed 1 January 1970) introduced the environmental impact statement for major federal actions. The UK planning act predates EIA, India's Act dates from 1986 and the EU Directive from 1985.

Further reading: Glasson and Therivel, Introduction to EIA

2 · Scoping and terms of reference · medium

What role does the 'no-project' (no action) alternative play in EIA?

  1. It is the alternative that the proponent must always select in the end, whatever the findings
  2. It is optional and may be ignored whenever the proponent prefers
  3. It describes the project after mitigation measures have been added
  4. It describes the future without the project and serves as the reference for comparison
Answer and working

D. It describes the future without the project and serves as the reference for comparison

The no-action alternative is the baseline against which other alternatives' impacts are measured. It need not be chosen, it is expected in good practice and required under NEPA, and the mitigated project is a separate alternative.

Further reading: NEPA; GT

3 · Impact identification: checklists, matrices, networks, overlays · easy

In the Leopold matrix, what two values are entered in each relevant cell?

  1. Cost and benefit, each in currency units
  2. Probability and frequency, each as a percentage
  3. Area and duration, each in hectares and years
  4. Magnitude and importance, each on a scale of 1 to 10
Answer and working

D. Magnitude and importance, each on a scale of 1 to 10

Leopold et al. (1971) asked for magnitude (extent or degree, a factual estimate) and importance (significance, a judgement), each scored 1–10. The matrix does not record costs, probabilities or area-duration pairs.

Further reading: Leopold et al., USGS Circular 645, 1971

4 · Impact identification: checklists, matrices, networks, overlays · medium

In the Battelle Environmental Evaluation System, how many parameter importance units (PIU) are distributed among the parameters?

  1. 1000
  2. 100
  3. 78
  4. 10
Answer and working

A. 1000

Battelle distributes 1000 PIU among 78 parameters in four categories (ecology, environmental pollution, aesthetics, human interest). 100 is a scale, 78 is the number of parameters.

Further reading: Dee et al. 1973

5 · Impact identification: checklists, matrices, networks, overlays · medium

Which identification method traces chains of primary, secondary and tertiary impacts from a project action?

  1. Simple checklist
  2. Impact network
  3. Overlay mapping
  4. Scaling checklist with ratings
Answer and working

B. Impact network

Networks such as the Sorensen network (1971) trace cause-effect chains, capturing indirect impacts. Checklists list items without chains; overlays show spatial patterns. An impact network is also called an impact tree.

Further reading: Sorensen 1971; GT

6 · Impact identification: checklists, matrices, networks, overlays · medium

What distinguishes a scaling checklist from a simple checklist?

  1. It lists fewer environmental components
  2. It traces chains of secondary impacts
  3. It adds a scale for rating the magnitude of each impact
  4. It overlays maps of sensitive areas
Answer and working

C. It adds a scale for rating the magnitude of each impact

Simple checklists list items; descriptive checklists add guidance; scaling checklists add magnitude ratings; questionnaire checklists pose structured questions. Chains are networks and maps are overlays.

Further reading: Canter, EIA

7 · Impact prediction and evaluation of significance · medium

Settlement and roadside businesses springing up along a new rural road are an example of what kind of impact?

  1. Direct impact
  2. Residual impact
  3. Induced impact
  4. Transboundary impact
Answer and working

C. Induced impact

Induced impacts arise from activities the project stimulates. Direct impacts are caused by the project itself (land take for the road); residual impacts remain after mitigation; transboundary impacts cross borders.

Further reading: Glasson and Therivel, Introduction to EIA

8 · Environmental management plans and monitoring · medium

Monitoring stack emissions to check that they meet the limits in a permit is which type of monitoring?

  1. Pre-project baseline monitoring
  2. Environmental effects monitoring
  3. Ecological impact monitoring
  4. Compliance monitoring
Answer and working

D. Compliance monitoring

Compliance monitoring checks conformity with standards and conditions. Baseline monitoring precedes the project; effects (impact) monitoring measures changes in the receiving environment to test predictions.

Further reading: Glasson and Therivel, Introduction to EIA

9 · Cumulative impact assessment · hard

Baseline PM10 at a village is 72 µg/m³ against a standard of 100 µg/m³. Three proposed plants are each predicted to add 10 µg/m³ there. What is the cumulative concentration?

  1. 82 µg/m³, which meets the standard
  2. 30 µg/m³, which meets the standard
  3. 172 µg/m³, which exceeds the standard
  4. 102 µg/m³, which exceeds the standard
Answer and working

D. 102 µg/m³, which exceeds the standard

Cumulative = 72 + 3 × 10 = 102 µg/m³ > 100: each plant alone (82) appears acceptable but together they breach the standard. 30 ignores the baseline; 172 adds the standard.

10 · Strategic environmental assessment · easy

Strategic environmental assessment (SEA) is applied to what?

  1. Individual factory buildings
  2. Single vehicles and machines
  3. Policies, plans and programmes
  4. Household consumption choices
Answer and working

C. Policies, plans and programmes

SEA assesses policies, plans and programmes (PPPs) early in decision-making; project EIA covers individual projects. Vehicles and households are not SEA subjects.

Further reading: Directive 2001/42/EC

Ten here, 39 in the app. The Laisha app has every practice question we have written to GATE in this subject, marked as you go, with timed papers, a jump-to-unanswered list and a certificate when you pass at 70 per cent.

Free for ten days, then one subscription of US$10 a month. We would rather say so here than have you find it later.

Practise the full set in Laisha →

Read the subject

Environmental Impact Assessment & Strategic Environmental AssessmentThe full study manual, free GATEFormat, sections and how it has changed

More GATE practice

Environmental MicrobiologyEnvironmental ChemistryAir & Noise Pollution: Monitoring & ControlMathematics & Statistics for Environmental ScienceWater & Wastewater TreatmentLife Cycle AssessmentClimate System ScienceEnergy, Environment & Agri-energy TransitionsHydrology & Water Resources for Environmental ScientistsSoil Contamination, Toxicology & RemediationEnvironmental Law, Policy & International AgreementsEarth Systems & Environmental GeoscienceSolid & Hazardous Waste ManagementSustainability Science: Concepts, History & EthicsWater Quality & Agricultural Non-point Source PollutionEnvironmental Management Systems, Auditing & StandardsCircular Economy & Bio-based ResourcesCarbon Accounting & Greenhouse Gas InventoriesAgricultural Water Conservation, Water Footprint & GovernanceBiodiversity Science & Conservation

Environmental Impact Assessment & Strategic Environmental Assessment for other exams

UGC NET · IndiaCertified Environmental Practitioner and specialist certifications · Australia / New ZealandQCI-NABET accreditation of EIA consultant organisations · India

Ask Laisha about this