LAISHA
Open Laisha

ICAR AIEEA-PG Surveying & Levelling: practice questions

ICAR AIEEA-PG — Agricultural Engineering & Technology (Major Subject Group 10) · India · National Testing Agency for ICAR

Original practice questions written to the published syllabus · not past papers
10worked here, free
109written to this exam in this subject
12syllabus units

What this subject covers

Measuring land, levels and volumes, from chain survey to total station and GNSS, and designing land grading.

In the exams: GATE AG Section 4 (surveying asked in 7 of 8 papers 2019–26); ICAR AIEEA-PG Unit VII; TNPSC Unit I; RPSC AAE Unit 1; NCEES PE surveying

What ICAR AIEEA-PG asks from it

ICAR AIEEA-PG — Agricultural Engineering & Technology (Unit VII)

Single-answer MCQs mixing definitions (types of bearings, contour characteristics, plane-table methods, theodolite axes, levelling terms) with quick calculations (back bearings, RLs, areas and volumes).

Where the 109 questions fall

How our questions for ICAR AIEEA-PG spread across the units of Surveying & Levelling. Difficulty: 43 easy, 46 medium, 20 hard.

Chain and tape surveying, including tape corrections12
Theodolite traversing and closing error12
Compass traversing and bearings10
Levelling: rise-and-fall and height-of-instrument methods10
Plane table surveying9
Reciprocal levelling9
Contouring9
GPS/GNSS surveying8
Computation of area: trapezoidal and Simpson's rules8
Earthwork volume computation8
Total station7
Land grading and levelling design7

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

1 · Compass traversing and bearings · easy

In a prismatic compass, the zero of the graduated ring is placed at the south end because

  1. sighting is through a prism opposite the object, so a north sight must read 0° at that end
  2. the compass reads quadrantal bearings
  3. the magnetic needle points south in the northern hemisphere, so zero must be set at the south
  4. the graduated ring rotates with the line of sight, so its zero must trail the sight vane by 180°
Answer and working

A. sighting is through a prism opposite the object, so a north sight must read 0° at that end

The ring is fixed to the needle and read through the prism at the eye end, diametrically opposite the object vane; to read 0° on a northward sight the zero must sit at the south end, and the figures are written inverted to read correctly through the prism. It reads whole-circle, not quadrantal, bearings, and its ring does not rotate with the sight (that is the surveyor's compass).

Further reading: Punmia, Jain and Jain, Surveying Vol. I

2 · Plane table surveying · medium

Which method of orienting a plane table is the more accurate?

  1. Back-sighting along a previously drawn line
  2. Estimating by eye
  3. Orienting by the sun's position
  4. Using the trough compass
Answer and working

A. Back-sighting along a previously drawn line

Back-sighting relies on a line already plotted, so it is as accurate as the plotting. The trough compass is quick but subject to local attraction and needle errors, so it is used only where no back station is available.

Further reading: Punmia, Jain and Jain, Surveying Vol. I

3 · Levelling: rise-and-fall and height-of-instrument methods · easy

A point on which both a foresight and a backsight are taken in a levelling line is called a

  1. intermediate station
  2. benchmark
  3. change point
  4. station point
Answer and working

C. change point

At a change (turning) point the foresight closes one set-up and the backsight opens the next, carrying the RL forward. A benchmark has a known RL; an intermediate station has only one reading.

Further reading: Punmia, Jain and Jain, Surveying Vol. I

4 · Contouring · easy

Which indirect method of contouring is most suitable for a long narrow strip such as a canal alignment?

  1. Radial lines from a single station
  2. Cross-sections at intervals along the centre line
  3. Grid of squares over the whole area
  4. Direct method on every contour
Answer and working

B. Cross-sections at intervals along the centre line

For a route the ground is profiled along the centre line and cross-sectioned at regular chainages, which directly gives the data for earthwork. Grids suit compact areas; radial tacheometry suits hilly country.

Further reading: Punmia, Jain and Jain, Surveying Vol. I

5 · Theodolite traversing and closing error · easy

A vernier theodolite has main-scale divisions of 20 minutes and 60 vernier divisions. What is its least count?

  1. 1 minute
  2. 20 minutes
  3. 20 seconds
  4. 3 minutes
Answer and working

C. 20 seconds

Least count = value of one main-scale division / number of vernier divisions = 20′/60 = 1/3′ = 20″.

Further reading: Punmia, Jain and Jain, Surveying Vol. I

6 · Theodolite traversing and closing error · medium

Taking the mean of face-left and face-right observations of a horizontal angle eliminates all of the following EXCEPT

  1. line of collimation not perpendicular to the horizontal axis
  2. horizontal axis not perpendicular to the vertical axis
  3. index error of the vertical circle
  4. error due to the vertical axis not being truly vertical
Answer and working

D. error due to the vertical axis not being truly vertical

Face changes reverse the sign of collimation, trunnion-axis and index errors, so they cancel in the mean. A tilted vertical axis tilts the horizontal axis the same way on both faces, so it does not cancel; careful levelling is the only remedy.

Further reading: Punmia, Jain and Jain, Surveying Vol. I

7 · Theodolite traversing and closing error · medium

The transit rule for balancing a traverse is preferred over Bowditch's rule when

  1. the traverse is open
  2. a compass is used for the bearings
  3. distances are measured more precisely than angles
  4. angles are measured more precisely than distances
Answer and working

D. angles are measured more precisely than distances

The transit rule distributes corrections in proportion to the size of each latitude and departure, which assumes angles are good and lengths poorer (theodolite with tape). Bowditch assumes equal effect of angular and linear errors and is the usual rule for compass traverses. Neither can be applied to an open traverse.

Further reading: Punmia, Jain and Jain, Surveying Vol. I

8 · GPS/GNSS surveying · hard

An RTK GNSS survey gives an ellipsoidal height of 18.6 m at a point where the geoid undulation N from the geoid model is −52.3 m. What is the orthometric height (height above the geoid)?

  1. 18.6 m
  2. -70.9 m
  3. 70.9 m
  4. -33.7 m
Answer and working

C. 70.9 m

H = h − N = 18.6 − (−52.3) = 70.9 m. Where the geoid lies below the ellipsoid (negative N), orthometric heights exceed ellipsoidal heights. Adding N gives -33.7 m; using the ellipsoidal height as if it were above mean sea level is the classic mistake.

Further reading: Ghilani and Wolf, Elementary Surveying

9 · Earthwork volume computation · medium

A 40 m long prismoid has end areas 12.0 and 24.0 m² and a mid-section area (computed from the mid-depth) of 17.5 m². What is its volume?

  1. 1413.3 m³
  2. 706.7 m³
  3. 720.0 m³
  4. 700.0 m³
Answer and working

B. 706.7 m³

V = (L/6)(A1 + 4Am + A2) = (40/6)(12 + 70 + 24) = 706.7 m³. Average end area gives 720.0 m³ (an overestimate for a prismoid); using L/3 doubles the answer because L here is the full length. 1413.3 m³ uses L/3; 700.0 m³ multiplies the mid-section area by the length.

Further reading: Punmia, Jain and Jain, Surveying Vol. I

10 · Land grading and levelling design · medium

When is the plane method of land-grading design NOT the best choice?

  1. On fields so irregular that a single plane would require excessive earth movement
  2. When the field is square
  3. On nearly uniform fields
  4. When least-squares fitting can be computed quickly by software instead of by hand calculation
Answer and working

A. On fields so irregular that a single plane would require excessive earth movement

A single best-fit plane is efficient for fairly uniform fields; where the surface is strongly irregular, profile, plan-inspection or contour-adjustment methods allow varying grades and cut far less earth.

Further reading: Schwab et al., Soil and Water Conservation Engineering

Ten here, 109 in the app. The Laisha app has every practice question we have written to ICAR AIEEA-PG in this subject, marked as you go, with timed papers, a jump-to-unanswered list and a certificate when you pass at 70 per cent.

Free for ten days, then one subscription of US$10 a month. We would rather say so here than have you find it later.

Practise the full set in Laisha →

Read the subject

Surveying & LevellingThe full study manual, free ICAR AIEEA-PGFormat, sections and how it has changed

More ICAR AIEEA-PG practice

Computer Programming, Data Structures & Agricultural InformaticsEngineering MathematicsEngineering ThermodynamicsHydraulic Drives & ControlsWatershed HydrologySoil Science for EngineersPost-Harvest Engineering of Horticultural CropsMachine DesignFluid Mechanics & Open Channel HydraulicsTheory of MachinesSoil MechanicsBio-energy Systems: Design & ApplicationsProbability, Statistics & Data AnalysisStrength of MaterialsRenewable Energy Sources (Solar, Wind)Electrical Machines & Power UtilisationIrrigation Engineering (Soil-Water-Plant, Conveyance, Surface Methods)Groundwater, Wells & PumpsWatershed Planning & ManagementRefrigeration, Air-Conditioning & Cold-Chain EngineeringEngineering Properties of Agricultural ProduceWater Resources Management, Floods & Canal SystemsEngineering Mechanics (Statics & Dynamics)Sprinkler & Micro-Irrigation Systems

Surveying & Levelling for other exams

GATE · IndiaRajasthan PSC · IndiaTamil Nadu PSC · IndiaASRB NET · IndiaNCEES PE Agricultural and Biological Engineering · USA

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.