What this subject covers

Measuring land, levels and volumes, from chain survey to total station and GNSS, and designing land grading.

In the exams: GATE AG Section 4 (surveying asked in 7 of 8 papers 2019–26); ICAR AIEEA-PG Unit VII; TNPSC Unit I; RPSC AAE Unit 1; NCEES PE surveying

What NCEES PE Agricultural and Biological Engineering asks from it

NCEES PE Agricultural and Biological Engineering

Surveying appears within common system applications: layout and grade staking, earthwork volumes, pond and channel grades, and interpretation of survey data in US customary or SI units.

Where the 20 questions fall

How our questions for NCEES PE Agricultural and Biological Engineering spread across the units of Surveying & Levelling. Difficulty: 0 easy, 10 medium, 10 hard.

Total station5
GPS/GNSS surveying5
Levelling: rise-and-fall and height-of-instrument methods2
Computation of area: trapezoidal and Simpson's rules2
Earthwork volume computation2
Chain and tape surveying, including tape corrections1
Contouring1
Land grading and levelling design1
Compass traversing and bearings1

7 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

1 · Levelling: rise-and-fall and height-of-instrument methods · hard

A staff is read from a level. The staff reading is 3.000 m when held vertical, but the staff was actually tilted 3° from the vertical in the direction of sight. What reading was observed (to 3 decimals), and what is the lesson?

  1. 3.000 m; tilt has no effect on a horizontal sight
  2. 2.996 m; a tilted staff reads too low
  3. 3.004 m; a tilted staff always reads too high
  4. 3.157 m; the error is proportional to sin θ
Answer and working

C. 3.004 m; a tilted staff always reads too high

The horizontal line cuts the tilted staff at a graduation of 3.000/cos 3° = 3.004 m. Tilt in any direction increases the reading, which is why the staffman rocks the staff and the minimum reading is taken.

Further reading: Punmia, Jain and Jain, Surveying Vol. I

2 · Total station · medium

An engineer must set out the corners of a farm pond from design coordinates using a total station. Which on-board function is used?

  1. Area computation
  2. Remote elevation measurement
  3. Stake-out
  4. Missing-line measurement
Answer and working

C. Stake-out

Stake-out computes the bearing and distance from the occupied station to each design point and guides the prism holder onto it. Missing-line measures between two observed points; remote elevation finds heights of inaccessible objects.

Further reading: Ghilani and Wolf, Elementary Surveying

3 · Total station · hard

A surveyor occupies an unknown point and observes angles and distances to two or more control points of known coordinates to fix the instrument's position. This total-station procedure is called

  1. backsight orientation on a known station
  2. resection (free-station set-up)
  3. intersection (from two known stations)
  4. stake-out
Answer and working

B. resection (free-station set-up)

Resection computes the occupied station's coordinates (and orientation) from observations to known points, which lets the instrument be placed wherever it has a good view. Intersection fixes a distant point from two known stations; ordinary orientation requires the instrument to be on a known point.

Further reading: Ghilani and Wolf, Elementary Surveying

4 · GPS/GNSS surveying · hard

An RTK GNSS survey gives an ellipsoidal height of 18.6 m at a point where the geoid undulation N from the geoid model is −52.3 m. What is the orthometric height (height above the geoid)?

  1. 18.6 m
  2. -70.9 m
  3. 70.9 m
  4. -33.7 m
Answer and working

C. 70.9 m

H = h − N = 18.6 − (−52.3) = 70.9 m. Where the geoid lies below the ellipsoid (negative N), orthometric heights exceed ellipsoidal heights. Adding N gives -33.7 m; using the ellipsoidal height as if it were above mean sea level is the classic mistake.

Further reading: Ghilani and Wolf, Elementary Surveying

5 · GPS/GNSS surveying · medium

Which GNSS technique gives centimetre-level positions in real time for staking out a land-grading design?

  1. Autonomous single-receiver code positioning
  2. Code-based differential GPS (DGPS)
  3. Long static carrier-phase sessions, processed later against reference stations
  4. Real-time kinematic (RTK) with a base station or reference network
Answer and working

D. Real-time kinematic (RTK) with a base station or reference network

RTK uses carrier-phase corrections from a base or network sent by radio or internet, and resolves positions to a few centimetres in seconds. Autonomous positioning is metre-level; code DGPS is sub-metre to metre; static gives very high accuracy but only after processing, not in real time.

Further reading: Ghilani and Wolf, Elementary Surveying

6 · Earthwork volume computation · hard

A borrow pit is laid out as four 10 m × 10 m squares (a 2 × 2 grid). Depths of cut at the four outer corners are 1.2, 0.8, 1.0 and 1.4 m; at the four mid-side points 1.1, 0.9, 1.3 and 1.2 m; and at the centre point 1.05 m. What is the volume of excavation?

  1. 442.2 m³
  2. 248.8 m³
  3. 440.0 m³
  4. 1760.0 m³
Answer and working

C. 440.0 m³

V = (A/4)(Σh1 + 2Σh2 + 4Σh4) with A = 100 m²: Σh1 = 4.4, Σh2 = 4.5, h4 = 1.05. V = 25(4.4 + 9.0 + 4.2) = 440.0 m³. Averaging all nine depths over 400 m² (442.2 m³) ignores how many squares share each corner. 248.8 m³ applies A/4 without the 2 and 4 weights; 1760.0 m³ uses A = 400 m² instead of 100 m².

Further reading: Punmia, Jain and Jain, Surveying Vol. I

7 · Land grading and levelling design · hard

A land-grading design gives total cut 1450 m³ and total fill 1320 m³. The engineer wants a cut:fill ratio of about 1.3 for this soil. What should be done?

  1. Increase the grid spacing
  2. Raise the design plane slightly
  3. Accept it: the current cut:fill ratio is already about 1.3, so no change is needed
  4. Lower the design plane slightly and recompute until cut/fill reaches about 1.3
Answer and working

D. Lower the design plane slightly and recompute until cut/fill reaches about 1.3

Current ratio = 1450/1320 = 1.10, below the target. Lowering the plane increases every cut and reduces every fill, raising the ratio; raising it would lower the ratio. The ratio allows for settlement and losses and its value depends on soil and conditions.

Further reading: Schwab et al., Soil and Water Conservation Engineering

Ten here, 20 in the app. The Laisha app has every practice question we have written to NCEES PE Agricultural and Biological Engineering in this subject, marked as you go, with timed papers, a jump-to-unanswered list and a certificate when you pass at 70 per cent.

Free for ten days, then one subscription of US$10 a month. We would rather say so here than have you find it later.

Practise the full set in Laisha →

Read the subject

Surveying & LevellingThe full study manual, free NCEES PE Agricultural and Biological EngineeringFormat, sections and how it has changed

More NCEES PE Agricultural and Biological Engineering practice

Hydraulic Drives & ControlsAgricultural Structures & Environmental ControlAgricultural Waste Management & Environmental EngineeringFood Quality, Safety & Process Plant DesignRemote Sensing, GIS & GNSS for Land & WaterSprinkler & Micro-Irrigation SystemsInstrumentation, Sensors & Process ControlEngineering Drawing, Graphics & CADProtected Cultivation & Greenhouse EngineeringMachine DesignProfessional Practice, Ethics & LawsIrrigation Engineering (Soil-Water-Plant, Conveyance, Surface Methods)Probability, Statistics & Data AnalysisElectrical Machines & Power UtilisationEngineering Economics, Project & Business ManagementBuilding Materials, Theory of Structures & ConstructionAgricultural Drones, Robotics & AutomationEngineering Properties of Agricultural Produce

Surveying & Levelling for other exams

ICAR AIEEA-PG · IndiaGATE · IndiaRajasthan PSC · IndiaTamil Nadu PSC · IndiaASRB NET · India

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.