Rajasthan PSC Soil & Water Conservation Engineering: practice questions

Rajasthan PSC — Assistant Agriculture Engineer (Agriculture Engineering syllabus) · India · Rajasthan Public Service Commission

Original practice questions written to the published syllabus · not past papers
7worked here, free
30written to this exam in this subject
10syllabus units

What this subject covers

Estimating erosion and designing the bunds, terraces, waterways, spillways, ponds and dams that control it.

In the exams: GATE AG Section 4 Soil & Water Erosion; ICAR AIEEA-PG Unit VII; ICAR AICE subject 40 Unit 5; NCEES PE erosion; PRC ABE land and water (32%); state PSCs

Where the 30 questions fall

How our questions for Rajasthan PSC spread across the units of Soil & Water Conservation Engineering. Difficulty: 14 easy, 11 medium, 5 hard.

Contour and graded bunds6
Farm ponds6
Gully control5
Wind erosion control and shelterbelts4
Bench and broad-base terraces3
Drop, drop-inlet and chute spillways2
Mechanics of water erosion1
Soil loss estimation: USLE, RUSLE and MUSLE1
Agronomic and biological conservation measures1
Earthen dams: seepage and stability1

7 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

1 · Contour and graded bunds · easy

Using VI = 0.3(S/3 + 2), with S in percent, the vertical interval between contour bunds on a 6% slope is:

  1. 2.4 m
  2. 0.6 m
  3. 4.0 m
  4. 1.2 m
Answer and working

D. 1.2 m

VI = 0.3 × (6/3 + 2) = 0.3 × 4 = 1.2 m. Forgetting to divide S by 3 gives 2.4; forgetting the 0.3 gives 4.0. Dropping the S/3 term gives 0.3 × 2 = 0.6 m.

Further reading: Suresh, R., Soil and Water Conservation Engineering

2 · Contour and graded bunds · easy

Surplus arrangements such as waste weirs are provided in contour bunds to:

  1. provide an inlet for irrigation water
  2. let runoff in excess of the design storage pass safely without breaching the bund
  3. drain all of the runoff from the field immediately so that no water is stored behind the bund
  4. measure the runoff from each strip
Answer and working

B. let runoff in excess of the design storage pass safely without breaching the bund

A bund stores only the design runoff. Waste weirs at low points or ends pass the excess in a controlled way; without them water overtops at the weakest point and breaches the bund.

Further reading: Suresh, R., Soil and Water Conservation Engineering

3 · Bench and broad-base terraces · hard

On a 20% slope the soil is deep enough to allow at most 0.5 m of cut at the inner edge of a level bench (vertical risers, balanced cut and fill). The widest bench that can be built without cutting below this depth is:

  1. 5.0 m
  2. 0.2 m
  3. 1.0 m
  4. 2.5 m
Answer and working

A. 5.0 m

For a balanced level bench, the cut at the inner edge is VI/2. Cut ≤ 0.5 m gives VI ≤ 1.0 m. W = 100 VI/S = 100 × 1.0/20 = 5.0 m. Treating 0.5 m as the VI gives 2.5 m, an unnecessarily narrow bench. 0.2 m multiplies VI by S/100 instead of dividing.

Further reading: Suresh, R., Soil and Water Conservation Engineering

4 · Gully control · easy

The usual order of the four stages of gully development is:

  1. formation, stabilisation, development, healing
  2. development, formation, stabilisation, healing
  3. formation, development, healing, stabilisation
  4. healing, formation, development, stabilisation
Answer and working

C. formation, development, healing, stabilisation

A gully first forms by scour of the topsoil, then enlarges and advances its head (most active stage), then vegetation begins to establish (healing), and finally the gully stabilises with a stable gradient and cover.

Further reading: Suresh, R., Soil and Water Conservation Engineering

5 · Gully control · medium

Check dams with an effective height of 0.9 m are placed in a gully with a bed slope of 6%, using the head-to-toe rule. The spacing between dams is:

  1. 5.4 m
  2. 15 m
  3. 1.5 m
  4. 0.15 m
Answer and working

B. 15 m

Head-to-toe: L = H / S = 0.9/0.06 = 15 m, so the crest of each dam is level with the toe of the next one upstream. Using S = 6 gives 0.15 m. H × S (0.9 × 6) gives 5.4 m, and reading 6% as 0.6 gives 1.5 m.

Further reading: Suresh, R., Soil and Water Conservation Engineering

6 · Gully control · medium

For an actively advancing gully with a large runoff-producing catchment above it, the first engineering step is to:

  1. divert or control runoff above the gully head and stabilise the head
  2. build check dams from the outlet upward only, starting at the gully mouth
  3. plant trees along the gully bed
  4. reshape the gully banks to 1:1
Answer and working

A. divert or control runoff above the gully head and stabilise the head

Gullies advance by head-cutting, so stopping runoff over the head and stabilising it comes first, alongside catchment treatment. Check dams and planting follow once the flow is controlled.

Further reading: Schwab et al. / Fangmeier et al., Soil and Water Conservation Engineering

7 · Farm ponds · hard

A pond must collect 4,000 m³ of runoff in a season with 500 mm of rain. If the seasonal runoff coefficient of the catchment is 0.2, the catchment area required is:

  1. 4 ha
  2. 0.8 ha
  3. 0.004 ha
  4. 0.16 ha
Answer and working

A. 4 ha

Runoff depth = 0.2 × 0.5 m = 0.1 m. Area = 4,000/0.1 = 40,000 m² = 4 ha. Forgetting the runoff coefficient gives 0.8 ha; using rainfall in mm without converting gives a tiny area. Working in mm without converting gives 40 m² = 0.004 ha, and multiplying by the coefficient gives 0.16 ha.

Further reading: Schwab et al. / Fangmeier et al., Soil and Water Conservation Engineering

Ten here, 30 in the app. The Laisha app has every practice question we have written to Rajasthan PSC in this subject, marked as you go, with timed papers, a jump-to-unanswered list and a certificate when you pass at 70 per cent.

Free for ten days, then one subscription of US$10 a month. We would rather say so here than have you find it later.

Practise the full set in Laisha →

Read the subject

Soil & Water Conservation EngineeringThe full study manual, free Rajasthan PSCFormat, sections and how it has changed

More Rajasthan PSC practice

Surveying & LevellingIrrigation Engineering (Soil-Water-Plant, Conveyance, Surface Methods)Farm Machinery & Equipment I — Tillage, Sowing, Planting, FertiliserTractor & Automotive Engines (IC Engines)Farm Machinery & Equipment II — Plant Protection, Harvesting, ThreshingFarm Machinery Management & EconomicsHydraulic Drives & ControlsWatershed HydrologySprinkler & Micro-Irrigation SystemsFarm Power SourcesMechanics of Tillage & Traction (Soil Dynamics)Tractor Systems & ControlsWater Resources Management, Floods & Canal SystemsHuman Engineering, Ergonomics & SafetyWatershed Planning & Management

Soil & Water Conservation Engineering for other exams

ICAR AIEEA-PG · IndiaTamil Nadu PSC · IndiaGATE · IndiaICAR AICE-JRF/SRF · India