LAISHA
Open Laisha

NCEES PE Agricultural and Biological Engineering Engineering Economics, Project & Business Management: practice questions

NCEES PE Agricultural and Biological Engineering · USA · NCEES (ASABE is the content partner)

Original practice questions written to the published syllabus · not past papers
6worked here, free
29written to this exam in this subject
9syllabus units

What this subject covers

Money and time in engineering decisions: discounting, costs, break-even, project appraisal, scheduling and starting a business.

In the exams: NCEES FE Engineering Economics 6–9 questions; NCEES PE engineering economics and project management; ICAR AICE subject 41 Unit 10; PRC ABE project management

Where the 29 questions fall

How our questions for NCEES PE Agricultural and Biological Engineering spread across the units of Engineering Economics, Project & Business Management. Difficulty: 2 easy, 15 medium, 12 hard.

Fixed and variable costs9
Replacement analysis6
Time value of money3
NPV, IRR, benefit-cost ratio and payback3
Depreciation methods2
Break-even analysis2
Project appraisal and detailed project reports2
Linear programming1
Entrepreneurship and marketing1

6 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

1 · Time value of money · medium

A project's benefits are forecast in constant prices of the base year. At which rate should they be discounted?

  1. At the market interest rate, because that is the rate lenders actually charge the project
  2. At the inflation rate alone, because constant-price flows change only with general inflation
  3. At the real interest rate, which excludes inflation just as constant-price cash flows do
  4. At the market rate plus the inflation rate, to allow for inflation over the whole project life
Answer and working

C. At the real interest rate, which excludes inflation just as constant-price cash flows do

The rule is consistency: constant (real) cash flows at the real rate, actual (then-current) cash flows at the market rate, which already contains inflation. Discounting constant-price benefits at the market rate removes inflation twice and understates worth; adding inflation to the market rate makes the error worse.

2 · NPV, IRR, benefit-cost ratio and payback · medium

A public irrigation scheme has present worth of benefits 5.2 million, first cost 3.0 million and present worth of operation and maintenance cost 1.0 million. Using the modified benefit-cost ratio, in which O&M cost is deducted from benefits, what is the ratio?

  1. 1.30
  2. 1.73
  3. 1.40
  4. 1.05
Answer and working

C. 1.40

Modified B/C = (benefits − O&M)/first cost = (5.2 − 1.0)/3.0 = 1.40. 1.30 is the conventional ratio, benefits/(first cost + O&M) = 5.2/4.0; 1.73 omits O&M entirely; 1.05 counts O&M on both sides, (5.2 − 1.0)/(3.0 + 1.0). Both correct forms agree that B/C > 1, so the scheme is acceptable.

3 · NPV, IRR, benefit-cost ratio and payback · hard

Machine X costs 600,000, lasts 5 years, has salvage 100,000 and costs 80,000 a year to run. Machine Y costs 900,000, lasts 10 years, has salvage 150,000 and costs 60,000 a year to run. At 10 %, which has the lower equivalent annual cost?

  1. Y, at about 197,100 a year against about 221,900 for X
  2. X, at about 221,900 a year against about 197,100 for Y
  3. X, because its first cost is lower by 300,000 and annual costs are similar
  4. Neither: lives of 5 and 10 years cannot be compared without a 10-year study
Answer and working

A. Y, at about 197,100 a year against about 221,900 for X

EUAC_X = 600,000(A/P,10 %,5) − 100,000(A/F,10 %,5) + 80,000 = 221,899; EUAC_Y = 900,000(A/P,10 %,10) − 150,000(A/F,10 %,10) + 60,000 = 197,059. Y is cheaper. Annual cost compares unequal lives directly under the repeatability assumption, so no extra study period is needed; first cost alone ignores life and running cost.

4 · Break-even analysis · hard

Owning a paddy transplanter costs 150,000 a year in ownership cost plus 900 per hectare to operate. A contractor charges 2,400 per hectare. Above what annual area is owning cheaper than hiring?

  1. 62.5 ha
  2. 166.7 ha
  3. 45.5 ha
  4. 100 ha
Answer and working

D. 100 ha

Set 150,000 + 900A = 2,400A, so A* = 150,000/(2,400 − 900) = 100 ha. Above 100 ha owning is cheaper. 62.5 ha ignores the owner's operating cost; 166.7 ha divides by the operating cost; 45.5 ha adds the two rates.

5 · Break-even analysis · hard

An electric pump set has annual fixed costs of 60,000 and running cost 15 per hour; a diesel set has fixed costs of 20,000 and running cost 55 per hour. Which statement is correct?

  1. The diesel set is cheaper for any use above 1,000 hours of pumping a year
  2. The electric set is cheaper for any use above 1,000 hours of pumping a year
  3. The electric set is cheaper only above 1,500 hours, where its fixed cost is recovered
  4. The two sets cost the same at every level of use because their totals are equal
Answer and working

B. The electric set is cheaper for any use above 1,000 hours of pumping a year

Equal annual cost: 60,000 + 15h = 20,000 + 55h, so h = 40,000/40 = 1,000 h. Above that, the electric set's lower running cost outweighs its higher fixed cost; below it, diesel is cheaper. Any first costs should be converted to annual amounts with the capital recovery factor before this comparison.

6 · Replacement analysis · medium

A defender's marginal cost of keeping it one more year is 140,000 and rising each year. The best challenger has a minimum equivalent annual cost of 150,000 at its economic life. What should be done?

  1. Replace the defender now, because its marginal cost is rising every year
  2. Keep the defender until it is fully depreciated in the firm's accounts
  3. Keep the defender for at least one more year and repeat the comparison next year
  4. Replace the defender now, because the challenger is a newer design
Answer and working

C. Keep the defender for at least one more year and repeat the comparison next year

The defender is cheaper for the coming year (140,000 < 150,000), so keeping it saves money now. Because its marginal cost is rising, it will soon exceed 150,000, and the comparison should be repeated each year. Book depreciation and novelty are not decision criteria.

Ten here, 29 in the app. The Laisha app has every practice question we have written to NCEES PE Agricultural and Biological Engineering in this subject, marked as you go, with timed papers, a jump-to-unanswered list and a certificate when you pass at 70 per cent.

Free for ten days, then one subscription of US$10 a month. We would rather say so here than have you find it later.

Practise the full set in Laisha →

Read the subject

Engineering Economics, Project & Business ManagementThe full study manual, free NCEES PE Agricultural and Biological EngineeringFormat, sections and how it has changed

More NCEES PE Agricultural and Biological Engineering practice

Hydraulic Drives & ControlsAgricultural Structures & Environmental ControlAgricultural Waste Management & Environmental EngineeringFood Quality, Safety & Process Plant DesignRemote Sensing, GIS & GNSS for Land & WaterSprinkler & Micro-Irrigation SystemsInstrumentation, Sensors & Process ControlEngineering Drawing, Graphics & CADProtected Cultivation & Greenhouse EngineeringMachine DesignProfessional Practice, Ethics & LawsIrrigation Engineering (Soil-Water-Plant, Conveyance, Surface Methods)Probability, Statistics & Data AnalysisElectrical Machines & Power UtilisationBuilding Materials, Theory of Structures & ConstructionSurveying & LevellingAgricultural Drones, Robotics & AutomationEngineering Properties of Agricultural Produce

Engineering Economics, Project & Business Management for other exams

Nepal Engineering Council Registration Exam · NepalAgricultural and Biosystems Engineers Licensure Examination · PhilippinesNCEES FE Other Disciplines · USAICAR AICE-JRF/SRF · India

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.