Agricultural and Biosystems Engineers Licensure Examination Engineering Economics, Project & Business Management: practice questions

Agricultural and Biosystems Engineers Licensure Examination (ABELE) · Philippines · Professional Regulatory Board of Agricultural and Biosystems Engineering, PRC

Original practice questions written to the published syllabus · not past papers
10worked here, free
53written to this exam in this subject
9syllabus units

What this subject covers

Money and time in engineering decisions: discounting, costs, break-even, project appraisal, scheduling and starting a business.

In the exams: NCEES FE Engineering Economics 6–9 questions; NCEES PE engineering economics and project management; ICAR AICE subject 41 Unit 10; PRC ABE project management

What Agricultural and Biosystems Engineers Licensure Examination asks from it

PRC Agricultural and Biosystems Engineers Licensure Examination

Project management, machinery cost analysis, depreciation and break-even problems set within the allied-subjects papers, solved with a non-programmable calculator.

Where the 53 questions fall

How our questions for Agricultural and Biosystems Engineers Licensure Examination spread across the units of Engineering Economics, Project & Business Management. Difficulty: 19 easy, 25 medium, 9 hard.

Fixed and variable costs8
Break-even analysis8
Entrepreneurship and marketing8
NPV, IRR, benefit-cost ratio and payback6
Depreciation methods6
CPM and PERT6
Time value of money5
Replacement analysis4
Project appraisal and detailed project reports2

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

1 · NPV, IRR, benefit-cost ratio and payback · hard

A grading line costs 240,000 and earns net receipts of 60,000 a year. What is its discounted payback period at 10 % a year, interpolating within the year?

  1. 4.0 years
  2. 5.4 years
  3. 6.0 years
  4. 3.6 years
Answer and working

B. 5.4 years

Cumulative discounted receipts: 60,000(P/A, 10 %, n) reaches 240,000 between year 5 (227,447) and year 6 (261,316); interpolation gives 5.4 years. 4.0 years is simple payback, 240,000/60,000, which ignores interest; discounted payback is always longer. 3.6 years compounds the receipts instead of discounting them (240,000/(60,000 × 1.1)).

2 · Depreciation methods · medium

A tractor costs 800,000, has a salvage value of 80,000 and a recovery period of 8 years. Using double declining balance, what is the depreciation in year 2?

  1. 150,000
  2. 200,000
  3. 135,000
  4. 90,000
Answer and working

A. 150,000

d = 2/n = 0.25. D1 = 0.25 × 800,000 = 200,000; BV1 = 600,000; D2 = 0.25 × 600,000 = 150,000. 200,000 is year 1; 135,000 wrongly applies the rate to B − S, but declining balance uses book value and ignores salvage until the floor is reached; 90,000 is straight line.

3 · Break-even analysis · easy

A spice-grinding unit has fixed costs of 600,000 a year, sells at 50 a kg and has variable costs of 30 a kg. What is its break-even output?

  1. 30,000 kg
  2. 12,000 kg
  3. 20,000 kg
  4. 7,500 kg
Answer and working

A. 30,000 kg

Q* = F/(p − v) = 600,000/(50 − 30) = 30,000 kg. 12,000 divides by price and 20,000 by variable cost; 7,500 adds them instead of subtracting. The contribution margin, p − v, is what covers fixed cost.

4 · Break-even analysis · medium

A spice-grinding unit has fixed costs of 600,000 a year, a price of 50 a kg and variable costs of 30 a kg. If it plans to sell 40,000 kg, what is its margin of safety as a percentage of planned sales?

  1. 25.0 %
  2. 33.3 %
  3. 75.0 %
  4. 20.0 %
Answer and working

A. 25.0 %

Break-even = 600,000/20 = 30,000 kg. Margin of safety = 40,000 − 30,000 = 10,000 kg = 10,000/40,000 = 25.0 % of planned sales. 33.3 % divides by break-even output instead; 75 % is break-even as a share of plan; 20 % is the contribution per kg read as a percentage.

5 · Break-even analysis · hard

An electric pump set has annual fixed costs of 60,000 and running cost 15 per hour; a diesel set has fixed costs of 20,000 and running cost 55 per hour. Which statement is correct?

  1. The diesel set is cheaper for any use above 1,000 hours of pumping a year
  2. The electric set is cheaper for any use above 1,000 hours of pumping a year
  3. The electric set is cheaper only above 1,500 hours, where its fixed cost is recovered
  4. The two sets cost the same at every level of use because their totals are equal
Answer and working

B. The electric set is cheaper for any use above 1,000 hours of pumping a year

Equal annual cost: 60,000 + 15h = 20,000 + 55h, so h = 40,000/40 = 1,000 h. Above that, the electric set's lower running cost outweighs its higher fixed cost; below it, diesel is cheaper. Any first costs should be converted to annual amounts with the capital recovery factor before this comparison.

6 · Replacement analysis · easy

A pump still works reliably, but a new model uses 30 % less energy for the same duty. The loss in value of the old pump for this reason is called:

  1. Physical depreciation from wear and tear
  2. Sunk cost of the original purchase price
  3. Obsolescence, or functional depreciation
  4. Salvage value at the end of its life
Answer and working

C. Obsolescence, or functional depreciation

Obsolescence is the loss of value caused by better technology or changed requirements, not by wear. Physical depreciation comes from use, corrosion and accidents. It is one of the main reasons assets are replaced before they wear out.

7 · CPM and PERT · medium

Activities and durations in days, with predecessors: A 4 (none), B 6 (none), C 5 (after A), D 3 (after A), E 4 (after B and D), F 2 (after C and E). What is the project duration?

  1. 24 days
  2. 11 days
  3. 12 days
  4. 13 days
Answer and working

D. 13 days

Forward pass: A 0–4, B 0–6, C 4–9, D 4–7, E starts at max(6, 7) = 7 and ends 11, F starts at max(9, 11) = 11 and ends 13. 24 days adds all durations as if in series; 11 days is path A–C–F and 12 days path B–E–F, both shorter than the critical path A–D–E–F.

8 · CPM and PERT · medium

An activity has a normal time of 10 days at a cost of 50,000 and a crash time of 6 days at a cost of 70,000. What is its cost slope?

  1. 5,000 per day
  2. 2,000 per day
  3. 7,000 per day
  4. 11,667 per day
Answer and working

A. 5,000 per day

Cost slope = (crash cost − normal cost)/(normal time − crash time) = (70,000 − 50,000)/(10 − 6) = 5,000 per day. 2,000 divides by the normal time; 7,000 divides the whole crash cost by 10; 11,667 divides crash cost by 6 days.

9 · CPM and PERT · medium

What does resource levelling do in project scheduling?

  1. It shortens critical activities by adding resources so the project finishes sooner
  2. It assigns every activity the same quantity of labour and machines each day
  3. It removes activities that use scarce resources from the project network
  4. It uses the float of non-critical activities to smooth daily resource demand
Answer and working

D. It uses the float of non-critical activities to smooth daily resource demand

Levelling uses the float of non-critical activities to reduce peaks and valleys in resource use without extending the project. Shortening critical activities with extra resources is crashing. If resources are too few even after levelling, resource-constrained scheduling extends the project.

10 · Entrepreneurship and marketing · easy

The plan-do-check-act cycle of continuous improvement is associated with:

  1. Frederick W. Taylor
  2. W. Edwards Deming
  3. Henri Fayol
  4. Philip Kotler
Answer and working

B. W. Edwards Deming

Deming popularised the PDCA (Shewhart) cycle as the core of quality improvement. Taylor founded scientific management, Fayol set out principles of administration, and Kotler is a marketing author.

Ten here, 53 in the app. The Laisha app has every practice question we have written to Agricultural and Biosystems Engineers Licensure Examination in this subject, marked as you go, with timed papers, a jump-to-unanswered list and a certificate when you pass at 70 per cent.

Free for ten days, then one subscription of US$10 a month. We would rather say so here than have you find it later.

Practise the full set in Laisha →

Read the subject

Engineering Economics, Project & Business ManagementThe full study manual, free Agricultural and Biosystems Engineers Licensure ExaminationFormat, sections and how it has changed

More Agricultural and Biosystems Engineers Licensure Examination practice

Engineering Drawing, Graphics & CADCrop Production & Protection for EngineersAquacultural & Forest Engineering (regional)Workshop Technology & ManufacturingAgricultural Waste Management & Environmental EngineeringBuilding Materials, Theory of Structures & ConstructionProfessional Practice, Ethics & LawsBio-energy Systems: Design & ApplicationsSoil Science for EngineersRenewable Energy Sources (Solar, Wind)Sprinkler & Micro-Irrigation SystemsFarm Power SourcesMachine DesignElectrical Machines & Power UtilisationFarm Machinery & Equipment I — Tillage, Sowing, Planting, FertiliserAgricultural Structures & Environmental ControlStrength of MaterialsFarm Machinery Management & EconomicsTheory of MachinesEngineering Thermodynamics

Engineering Economics, Project & Business Management for other exams