ASRB NET and ARS / SMS / STO recruitment · India · Agricultural Scientists Recruitment Board (ICAR)
Original practice questions written to the published syllabus · not past papersTaking an agricultural project from idea to appraisal to delivery, and building an agri-enterprise: feasibility, NPV and IRR, PERT/CPM, business plans and incubation.
In the exams: agribusiness management PhD entrance and fellowship examinations, project management and entrepreneurship (heavy); agricultural economics PhD entrance and fellowship examinations, project appraisal (heavy); agricultural master's entrance examinations, time value of money and entrepreneurship (heavy); agricultural development bank officer recruitment, project appraisal (present)
How our questions for ASRB NET and ARS / SMS / STO recruitment spread across the units of Project Management, Appraisal & Agri-Entrepreneurship. Difficulty: 8 easy, 30 medium, 17 hard.
| CPM and PERT | 8 | |
| Theories of entrepreneurship and entrepreneurial competencies | 6 | |
| Social cost-benefit analysis | 5 | |
| Project risk | 5 | |
| Incubation, IPR and technology commercialisation | 5 | |
| Discounted measures: NPV, IRR, BCR and profitability index | 4 | |
| Financial and economic feasibility | 4 | |
| Scheduling and resource allocation | 4 | |
| Cost overruns, monitoring and mid-course correction | 3 | |
| Undiscounted measures: payback and ARR | 2 | |
| The project cycle | 2 | |
| Market and technical feasibility | 2 | |
| Setting up a micro, small or medium enterprise | 2 | |
| Time value of money: compounding and discounting | 1 | |
| Business plans | 1 | |
| Women's, self-help group and family enterprises | 1 |
Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.
The nominal discount rate is 12% and expected inflation is 5%. What is the exact real discount rate?
C. 6.67%
Fisher relation: real = (1 + nominal)/(1 + inflation) − 1 = 1.12/1.05 − 1 = 6.67%. 7.00% is the simple-subtraction approximation; 17.60% multiplies the two factors instead of dividing; 5% is the inflation rate itself. Real cash flows must be discounted at the real rate.
Further reading: Brealey, Myers and Allen, Principles of Corporate Finance
Two mutually exclusive projects cost 1,000 currency units each. A returns 1,500 currency units in year 3 only (IRR 14.5%). B returns 950 currency units, 150 and 100 in years 1-3 (IRR 15.5%). The opportunity cost of capital is 10%. Which should be chosen and why?
D. A, because its NPV at 10% (about 127) exceeds B's (about 63)
For mutually exclusive projects rank by NPV at the opportunity cost of capital (or by the IRR of the incremental flows). NPV(A) = 1,500 × 0.7513 − 1,000 = 127; NPV(B) = 63. The NPV curves cross at about 13.8% (the Fisher rate); below that A is better. Ranking by IRR is the classic error because IRR ignores scale and timing differences.
Further reading: Gittinger, Economic Analysis of Agricultural Projects (1982)
A project has NPV 60,000 currency units and the present value of its benefits is 400,000 currency units. By what percentage can benefits fall before the project ceases to be worthwhile (the switching value)?
A. 15.0%
Benefits can fall by the NPV before it reaches zero: 60,000/400,000 = 15.0%. 85% is the remaining share of benefits; 17.6% divides by PV of costs (60,000/340,000), which is the switching value for costs, not benefits. 6.7% inverts the ratio (400,000/60,000 = 6.67).
Further reading: Gittinger, Economic Analysis of Agricultural Projects (1982)
A seed-processing plant has an NPV of −20,000 currency units in a bad season (probability 0.25), 50,000 currency units in a normal season (0.50) and 90,000 currency units in a good season (0.25). What is its expected NPV?
A. 42,500
Expected NPV = Σ p × NPV = 0.25(−20,000) + 0.5(50,000) + 0.25(90,000) = −5,000 + 25,000 + 22,500 = 42,500 currency units. 40,000 currency units is the unweighted mean; 50,000 currency units is the most likely value; 120,000 currency units is the unweighted sum. (Its standard deviation is about 39,607 currency units.)
Further reading: Prasanna Chandra, Projects
Which probability distribution does PERT assume for the duration of an individual activity?
B. Beta distribution
The three-point estimate te = (a + 4m + b)/6 derives from the beta distribution, which is bounded and can be skewed. The normal distribution is applied to the total project duration through the central limit theorem, not to each activity.
Further reading: Taha, Operations Research: An Introduction
Which statement correctly contrasts CPM and PERT?
B. CPM uses single, known activity times; PERT uses three time estimates to handle uncertainty
CPM, developed for plant construction and maintenance with DuPont, assumes deterministic times and adds time-cost trade-offs; PERT, developed for the US Navy's Polaris programme, treats durations as random. Both model precedence.
Further reading: Taha, Operations Research: An Introduction
Which of these is NOT one of the six aspects of project preparation listed by Gittinger?
C. Political
Gittinger's six aspects are technical; institutional-organisational-managerial; social; commercial; financial; and economic. Political considerations matter in practice but are not one of his analytical aspects.
Further reading: Gittinger, Economic Analysis of Agricultural Projects (1982)
In a logical framework matrix, what are the four columns?
C. Narrative summary, objectively verifiable indicators, means of verification, assumptions
Goal, purpose, outputs and activities are the rows (the hierarchy of objectives). The columns describe each level, how its achievement will be measured, where the evidence comes from, and what external conditions must hold.
Further reading: USAID logical framework; Gittinger (1982)
Which of the following is NOT one of Schumpeter's five types of 'new combinations'?
D. Reducing wages to lower production cost
The five are: a new good or quality; a new method of production; a new market; a new source of raw material or half-manufactured goods; and a new organisation of an industry (creating or breaking a monopoly). Cutting wages is not innovation.
Further reading: Schumpeter, The Theory of Economic Development
Personal entrepreneurial competencies as used in the UNCTAD Empretec programme are grouped into three clusters. Which set is correct?
A. Achievement, planning, power
Achievement covers opportunity-seeking and initiative, persistence, fulfilling commitments, demand for quality and efficiency, and calculated risk-taking; planning covers goal-setting, information-seeking and systematic planning and monitoring; power covers persuasion and networking and independence and self-confidence. Motivation-hygiene is Herzberg's job-satisfaction theory.
Further reading: UNCTAD Empretec programme materials
Ten here, 55 in the app. The Laisha app has every practice question we have written to ASRB NET and ARS / SMS / STO recruitment in this subject, marked as you go, with timed papers, a jump-to-unanswered list and a certificate when you pass at 70 per cent.