ASRB NET Water Resources Management, Floods & Canal Systems: practice questions

ASRB NET — Farm Machinery & Power / Land & Water Management Engineering / Agricultural Structures & Process Engineering · India · Agricultural Scientists Recruitment Board (ICAR)

Original practice questions written to the published syllabus · not past papers
10worked here, free
57written to this exam in this subject
9syllabus units

What this subject covers

Managing water at the scale of reservoirs, canals and river basins, including floods and farmer participation.

In the exams: ICAR AICE subject 40 Units 7–8; ICAR AIEEA-PG Unit VII; electives in the ICAR 6th Deans' Committee B.Tech

What ASRB NET asks from it

ASRB NET — Land & Water Management Engineering

PG-level concepts: reservoir yield and operation, sediment management, IWRM, basin planning, participatory management and water quality.

Where the 57 questions fall

How our questions for ASRB NET spread across the units of Water Resources Management, Floods & Canal Systems. Difficulty: 11 easy, 31 medium, 15 hard.

Water resources of a country11
Water quality management10
Reservoirs8
Flood control measures7
Water users' associations and participatory irrigation management7
Canal operation4
Flood estimation4
Minor irrigation4
Diversion works2

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

1 · Water resources of a country · easy

Which allocation doctrine gives the holder of the oldest water right first call on supply during a shortage?

  1. Equitable and reasonable utilisation
  2. Riparian doctrine
  3. Prior appropriation
  4. Proportional sharing
Answer and working

C. Prior appropriation

Under prior appropriation ('first in time, first in right'), senior rights are met first in shortage, as in the western USA. Riparian doctrine ties rights to land bordering water; proportional sharing cuts everyone by the same fraction; equitable utilisation is the international-law principle for shared rivers.

Further reading: Loucks and van Beek, Water Resource Systems Planning and Management

2 · Water resources of a country · medium

What does an environmental flow assessment for a river basin plan specify?

  1. The minimum flow that keeps hydropower turbines above their cavitation limit at the dam in the dry season
  2. The surplus flow that can be transferred to another basin after the basin's own irrigation needs are met
  3. The quantity, timing and quality of flow needed to sustain the river ecosystem and people relying on it
  4. The flood flow that the river must be able to pass within its natural banks without overtopping them
Answer and working

C. The quantity, timing and quality of flow needed to sustain the river ecosystem and people relying on it

Environmental flows describe the flow regime, not only a minimum, needed for ecosystems and the livelihoods depending on them. Bankfull capacity, turbine operation and transferable surplus are engineering quantities that a basin plan computes separately.

Further reading: Loucks and van Beek, Water Resource Systems Planning and Management

3 · Reservoirs · hard

A catchment of 800 km² yields 1,200 t/km² of sediment a year to a reservoir with 95% trap efficiency. The deposit's dry bulk density is 1.2 t/m³. What volume of sediment is deposited each year?

  1. 0.91 Mm³
  2. 0.76 Mm³
  3. 1.09 Mm³
  4. 0.80 Mm³
Answer and working

B. 0.76 Mm³

Mass trapped = 800 × 1,200 × 0.95 = 912,000 t; volume = 912,000 ÷ 1.2 = 760,000 m³. 0.80 omits trap efficiency; 0.91 forgets to divide by bulk density; 1.09 multiplies by 1.2 instead of dividing.

Further reading: Morris and Fan, Reservoir Sedimentation Handbook

4 · Reservoirs · medium

What is a hedging rule in reservoir operation?

  1. Holding the reservoir at full level throughout the monsoon so that no inflow is ever lost
  2. Releasing the full demand whenever water is available and spilling only when the reservoir is full
  3. Releasing extra water ahead of a forecast flood to create space in the flood cushion
  4. Deliberately releasing less than full demand early in a drought to avoid a larger shortage later
Answer and working

D. Deliberately releasing less than full demand early in a drought to avoid a larger shortage later

Hedging accepts small early shortages to avoid a deep later one. Releasing full demand whenever possible is the standard operating policy; releasing ahead of a forecast flood is pre-release for flood control.

Further reading: Loucks and van Beek, Water Resource Systems Planning and Management

5 · Reservoirs · hard

In a multipurpose reservoir, what is the central operating conflict during the flood season?

  1. Flood control wants the pool kept low for a cushion, while conservation wants it high to secure refill
  2. Navigation wants constant releases, while flood control wants releases only after the monsoon ends
  3. Hydropower wants the pool low for maximum head, while irrigation wants it high for gravity supply to canals
  4. Sediment flushing needs the pool full, while water supply needs it empty before the monsoon
Answer and working

A. Flood control wants the pool kept low for a cushion, while conservation wants it high to secure refill

The flood cushion must be empty when floods come, but conservation purposes need the reservoir full by the end of the season. Hydropower wants a high pool for head, not a low one; flushing needs a drawn-down pool, not a full one.

Further reading: Loucks and van Beek, Water Resource Systems Planning and Management

6 · Flood control measures · medium

Which problem is commonly caused by long flood embankments along an aggrading alluvial river?

  1. Floods downstream become smaller because the embankments store most of the flood volume
  2. Groundwater levels in the protected area rise permanently above the ground surface
  3. The river bed degrades rapidly, undermining bridge piers and weirs far upstream of the reach
  4. The river bed rises between the embankments, increasing the consequence of a breach
Answer and working

D. The river bed rises between the embankments, increasing the consequence of a breach

Confined sediment deposits between embankments, raising the bed and flood levels, so breaches become more damaging; embankments also cause drainage congestion behind them. They store little volume, so they do not reduce downstream floods.

Further reading: WMO/GWP Integrated Flood Management

7 · Minor irrigation · medium

Why must tanks in a South Indian or Sri Lankan cascade be rehabilitated as a group rather than one at a time?

  1. All tanks in a cascade share a single sluice, so one cannot be repaired without closing all of the others
  2. Cascade tanks are always owned by one landholder, so a single legal approval covers all the tanks together
  3. Tanks in a cascade have no catchment of their own and depend entirely on supply from a canal system
  4. Each tank's surplus and drainage feed the next tank down the valley, so upstream changes alter supply downstream
Answer and working

D. Each tank's surplus and drainage feed the next tank down the valley, so upstream changes alter supply downstream

Cascades are hydrologically linked: raising one bund or desilting one tank changes what the next receives and the flood passing down. Each tank has its own sluice and catchment.

Further reading: FAO / IWMI studies of tank cascades

8 · Water users' associations and participatory irrigation management · easy

What distinguishes irrigation management transfer from participatory irrigation management?

  1. Transfer applies only to groundwater schemes and tubewells; participation applies only to canal systems
  2. Transfer hands management of part or all of a system to users; participation involves them alongside the agency
  3. Transfer gives users ownership of the dam and headworks; participation gives them only the main canal
  4. Transfer means users pay the agency a higher fee each season; participation means they pay no fee at all
Answer and working

B. Transfer hands management of part or all of a system to users; participation involves them alongside the agency

PIM involves users in planning, operation, maintenance and finance; IMT shifts responsibility (sometimes ownership) to user organisations, usually below a stated level. Neither is defined by fee level or water source.

Further reading: FAO / IWMI reviews of irrigation management transfer

9 · Water users' associations and participatory irrigation management · medium

Which is one of Elinor Ostrom's design principles for long-lived common-pool resource institutions such as irrigation systems?

  1. Fixed rules set nationally and applied identically to every system
  2. Management only by a government agency without user involvement
  3. Graduated sanctions for members who break the rules
  4. Equal water shares for all members regardless of their contributions
Answer and working

C. Graduated sanctions for members who break the rules

Ostrom's principles include clear boundaries, rules suited to local conditions with benefits proportional to contributions, collective choice, monitoring, graduated sanctions, conflict resolution, recognition of rights to organise, and nesting. Equal shares regardless of contribution and uniform national rules contradict them.

Further reading: Ostrom, Governing the Commons, 1990

10 · Water users' associations and participatory irrigation management · medium

Which country transferred the management of its irrigation districts to water user associations on a large scale from about 1989?

  1. Japan
  2. Egypt
  3. Australia
  4. Mexico
Answer and working

D. Mexico

Mexico's transfer programme, from about 1989, handed irrigation districts to user associations and is widely studied. Japan has long-established land improvement districts; Egypt and Australia followed different paths.

Further reading: FAO / IWMI reviews of irrigation management transfer

Ten here, 57 in the app. The Laisha app has every practice question we have written to ASRB NET in this subject, marked as you go, with timed papers, a jump-to-unanswered list and a certificate when you pass at 70 per cent.

Free for ten days, then one subscription of US$10 a month. We would rather say so here than have you find it later.

Practise the full set in Laisha →

Read the subject

Water Resources Management, Floods & Canal SystemsThe full study manual, free ASRB NETFormat, sections and how it has changed

More ASRB NET practice

Workshop Technology & ManufacturingPost-Harvest Engineering of Horticultural CropsAgricultural Drones, Robotics & AutomationEngineering Properties of Agricultural ProduceFood Quality, Safety & Process Plant DesignRefrigeration, Air-Conditioning & Cold-Chain EngineeringPrecision Agriculture & System ManagementBio-energy Systems: Design & ApplicationsSoil Science for EngineersPost-Harvest Engineering of Cereals, Pulses & OilseedsFood & Dairy EngineeringHeat & Mass TransferStorage Engineering, Material Handling & PackagingAgricultural Drainage EngineeringFarm Machinery & Equipment II — Plant Protection, Harvesting, ThreshingHydraulic Drives & ControlsMachine DesignRenewable Energy Sources (Solar, Wind)Theory of MachinesWatershed Planning & ManagementFarm Power SourcesFarm Machinery Management & EconomicsSoil MechanicsFluid Mechanics & Open Channel Hydraulics

Water Resources Management, Floods & Canal Systems for other exams

ICAR AICE-JRF/SRF · IndiaICAR AIEEA-PG · IndiaTamil Nadu PSC · IndiaRajasthan PSC · India

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.