GATE Water Resources Management, Floods & Canal Systems: practice questions

GATE — Agricultural Engineering (AG) · India · IITs and IISc on rotation (2026: IIT Guwahati)

Original practice questions written to the published syllabus · not past papers
10worked here, free
16written to this exam in this subject
4syllabus units

About GATE

GATE — Agricultural Engineering (AG) is a postgraduate admission exam run by IITs and IISc on rotation (2026: IIT Guwahati), for candidates in India. Computer-based, 3 hours, 100 marks (15 General Aptitude + 85 technical: 25 one-mark and 30 two-mark questions). MCQ, MSQ and NAT; negative marking on MCQ only (−1/3 for one-mark, −2/3 for two-mark); no partial credit on MSQ. On-screen virtual calculator.

Source: gate2026.iitg.ac.in.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Water Resources Management, Floods & Canal Systems in GATE

Hydrology section numericals that overlap this subject: flood frequency (return period, risk, Gumbel), rational method, unit hydrograph application and Muskingum routing; reservoir capacity calculations.

Managing water at the scale of reservoirs, canals and river basins, including floods and farmer participation.

Our 16 GATE questions in this subject: 3 easy, 7 medium, 6 hard, across 4 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to GATE and are not shown on any other exam's page.

Question 1 · hard

Monthly inflows to a site over a typical year are 20, 35, 60, 80, 45, 25, 12, 8, 5, 4, 6 and 10 Mm³. Using the sequent peak method, what live storage is needed to supply a uniform 20 Mm³ per month?

  1. 16 Mm³
  2. 110 Mm³
  3. 75 Mm³
  4. 70 Mm³
Answer and working

C. 75 Mm³

K_t = max(0, K_(t−1) + 20 − Q_t). Deficits build in the six months of 12, 8, 5, 4, 6 and 10: 8 + 12 + 15 + 16 + 14 + 10 = 75 Mm³ (the record is run twice; the maximum is 75). 16 is the worst single month; 70 is the annual surplus 310 − 240; 110 is the storage for a 25 Mm³ draft.

Question 2 · hard

A weir floor 30 m long has a single downstream cutoff 5 m deep and holds a head of 4 m. By Khosla's exit gradient formula, what is the exit gradient?

  1. About 1/4.4
  2. About 1/7.4
  3. About 1/3.9
  4. About 1/1.25
Answer and working

B. About 1/7.4

α = b/d = 6; λ = [1 + √37]/2 = 3.54; G_E = (H/d)/(π√λ) = 0.8 ÷ (π × 1.882) = 0.135 ≈ 1/7.4. 1/1.25 is H/d alone (0.8); 1/4.4 divides by λ instead of π√λ; 1/3.9 omits √λ (0.8 ÷ π).

Question 3 · easy

Using the rational method, what is the peak runoff from a 2.5 km² catchment with runoff coefficient 0.35 and design rainfall intensity 60 mm/h?

  1. 14.6 m³/s
  2. 41.7 m³/s
  3. 52.5 m³/s
  4. 1.46 m³/s
Answer and working

A. 14.6 m³/s

Q = CiA/3.6 = 0.35 × 60 × 2.5 ÷ 3.6 = 14.6 m³/s. 52.5 forgets the 3.6; 1.46 slips a decimal; 41.7 omits C.

Question 4 · easy

Using Dickens' formula Q = C·A^(3/4) with C = 11.4 (Q in m³/s, A in km²), what is the peak flood from a 400 km² catchment?

  1. About 230 m³/s
  2. About 4,560 m³/s
  3. About 1,020 m³/s
  4. About 620 m³/s
Answer and working

C. About 1,020 m³/s

Q = 11.4 × 400^0.75 = 11.4 × 89.4 = 1,020 m³/s. 4,560 uses A to the power 1; 620 uses A^(2/3) (Ryves' exponent); 230 uses A^0.5.

Question 5 · medium

A 6-h unit hydrograph has a peak of 50 m³/s per cm. A storm gives 3 cm of effective rainfall in 6 h and baseflow is 20 m³/s. What is the peak of the flood hydrograph?

  1. 170 m³/s
  2. 150 m³/s
  3. 210 m³/s
  4. 70 m³/s
Answer and working

A. 170 m³/s

Direct runoff peak = 3 × 50 = 150 m³/s; add baseflow 20: 170 m³/s. 150 omits baseflow; 70 adds instead of multiplying; 210 multiplies the baseflow by the rainfall depth as well, 3 × (50 + 20).

Question 6 · medium

The ordinates of a 6-h unit hydrograph for 1 cm of effective rainfall, read at 6-h intervals, sum to 300 m³/s. What is the catchment area?

  1. 6,480 km²
  2. 108 km²
  3. 64.8 km²
  4. 648 km²
Answer and working

D. 648 km²

Volume = 300 × 6 × 3,600 = 6.48 × 10⁶ m³ = 1 cm over A, so A = 6.48 × 10⁶ ÷ 0.01 = 648 × 10⁶ m² = 648 km². 108 uses a 1-h interval; 64.8 and 6,480 are decimal slips.

Question 7 · hard

A structure has a design life of 25 years and the accepted risk of failure in that time is 10%. What design return period is needed?

  1. About 25 years
  2. About 2.5 years
  3. About 238 years
  4. 250 years
Answer and working

C. About 238 years

T = 1/[1 − (1 − 0.10)^(1/25)] = 1 ÷ 0.0042 = 237.8 years. 250 comes from the approximation T ≈ n/R; 25 sets T equal to the life; 2.5 is n × R.

Question 8 · medium

Annual flood peaks for 40 years are ranked in descending order. Using the Weibull plotting position, what return period is assigned to the second-largest flood?

  1. 13.7 years
  2. 41.0 years
  3. 20.0 years
  4. 20.5 years
Answer and working

D. 20.5 years

T = (n + 1)/m = 41 ÷ 2 = 20.5 years. 20.0 uses n/m; 41 is the top-ranked flood; 13.7 uses rank 3.

Question 9 · hard

Annual flood peaks at a site have mean 1,200 m³/s and standard deviation 400 m³/s. Using Gumbel's method with K_T = −(√6/π)[0.5772 + ln ln(T/(T−1))] (very long record), what is the 100-year flood?

  1. About 1,722 m³/s
  2. About 2,455 m³/s
  3. About 2,018 m³/s
  4. About 2,237 m³/s
Answer and working

B. About 2,455 m³/s

K100 = −0.7797 × [0.5772 + ln ln(100/99)] = −0.7797 × [0.5772 − 4.6002] = 3.137; Q = 1,200 + 3.137 × 400 = 2,455 m³/s. 2,237 is the 50-year flood (K = 2.592); 1,722 is the 10-year flood; 2,018 is the 25-year flood (K = 2.044).

Question 10 · hard

For Muskingum routing with K = 10 h and X = 0.25, which time step keeps all routing coefficients non-negative?

  1. Δt = 6 h
  2. Δt = 2 h
  3. Δt = 20 h
  4. Δt = 16 h
Answer and working

A. Δt = 6 h

Coefficients stay non-negative when 2KX ≤ Δt ≤ 2K(1 − X), i.e. 5 h ≤ Δt ≤ 15 h. Only 6 h lies in the range; 2 h makes C0 negative; 16 h and 20 h make C2 negative.

A study plan for Water Resources Management, Floods & Canal Systems in GATE

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (81% of the 16 questions): Flood estimation (9, 56%); Flood control measures (4, 25%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Diversion works (2, 13%); Reservoirs (1, 6%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Leave time for the hard ones: Reservoirs (1 hard of 1), Flood control measures (2 hard of 4), Diversion works (1 hard of 2).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  4. Bank the easy marks: Flood estimation (3 easy of 9).

    Do these early in revision so they are fast on the day.

  5. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — GATE Water Resources Management, Floods & Canal Systems

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers